During enterprise holiday shutdowns, vacuum brazing furnaces remain idle for extended periods, making their insulation layers and structural components prone to absorbing moisture and atmospheric impurities. Resuming operations immediately without treatment can easily lead to quality issues—such as insufficient vacuum levels, workpiece oxidation, pinholes, and debonding—while also accelerating the aging of the vacuum system. To standardize shutdown and restart procedures and ensure product quality and equipment stability, this simplified oven drying specification has been established.
Equipment shutdown states are categorized into four levels based on the duration of the shutdown and whether the furnace chamber was exposed to air (breaking vacuum), with differentiated oven drying processes applied for each:
Shutdown of less than 8 hours (furnace door unopened; chamber sealed and pressure maintained): No full oven drying cycle is required; production can resume with normal loading, provided the low-temperature vacuum holding phase (150–300°C) is extended by 30–60 minutes.
Overnight shutdown exceeding 12 hours (vacuum or slight positive nitrogen pressure maintained): An empty-furnace drying and degassing cycle is required. Heat to 650–700°C and hold for 1–2 hours to prevent issues such as substandard vacuum levels, oxidation spots, and pinhole defects upon restart.
Shutdown exceeding 48 hours with the furnace opened (chamber fully exposed to air and moisture): An empty-furnace dehumidification and degassing cycle is mandatory. Control the temperature between 500–700°C and preheat the diffusion pump for at least one hour; strict adherence is required for high-precision brazing applications, such as in the aerospace industry.
Shutdown exceeding 7 days (deep moisture absorption in the insulation layer): A stepped oven drying process must be used: Room temperature to 200°C (heating rate ≤10°C/min), hold for 2–4 hours for low-temperature dehumidification; 200°C to 500°C (heating rate 5–8°C/min), hold for 2–4 hours for medium-temperature degassing; 500°C to 700°C (heating rate ≤5°C/min), hold for 2–4 hours for deep degassing. Rapid heating directly to the brazing temperature is strictly prohibited.
Following a shutdown exceeding two weeks or a major equipment overhaul, an 8-hour+ staged bake-out process must be performed. Each temperature stage requires a holding time of at least 2 hours; production may only resume after the furnace has cooled to room temperature and passed the pressure rise rate test.
Applicable regardless of shutdown duration: long-term shutdown or furnace downtime ≥7 days; downtime ≥3 days during humid seasons; water ingress, air leakage, or furnace body disassembly (e.g., opening the lid for maintenance, replacing seals, excessive cold-state leakage, or moisture/water ingress); abnormal vacuum levels (failure to reach ≤5 Pa after 1 hour of standard evacuation); pressure rise rate >0.5 Pa/h; and new furnaces or post-overhaul status (where furnace lining—graphite felt or ceramic fiber—is newly installed or extensively replaced), requiring full execution of the standard bake-out process.
For bake-outs following routine shutdowns, strictly control the heating rate: ≤10°C/min from room temperature to 200°C, and ≤5–8°C/min above 200°C, to prevent thermal shock.
Key holding stages are 200°C ±20°C, 500°C ±20°C, and 700°C ±20°C, with holding times of 2–4 hours per stage to progressively remove physically adsorbed water, chemically bound water, and impurity gases. Allow natural cooling after bake-out; conduct the pressure rise rate test once the furnace temperature drops below 100°C. For long-term shutdowns or overhauled equipment, holding times may be extended to 8–12 hours, and additional intermediate constant-temperature stages may be added. Actual processing should prioritize the equipment manufacturer’s standard PLC program, with flexible adjustments based on furnace type (aluminum brazing, single/dual-chamber) and tooling load.
With the equipment cooled to below 100°C and the chamber sealed, monitor pressure changes for at least 1 hour to calculate the pressure rise rate.
Acceptance criteria: ≤0.2–0.3 Pa/h for high-end precision brazing; ≤0.5 Pa/h for general industrial production; and a standard upper tolerance limit of 0.67 Pa/h. If parameters exceed limits, the furnace must be re-baked, and potential leak points—such as sealing rings, piping, and weld seams—must be inspected.
For short-term shutdowns without breaking the vacuum, only the low-temperature evacuation process needs optimization; for overnight shutdowns, a standard 700°C bake-out is required; for shutdowns exceeding two days, the overall thermal insulation duration must be extended; and for shutdowns exceeding one week or following major equipment overhauls, a stepped bake-out process and pressure rise rate verification are mandatory. All bake-out operations must be performed with an empty furnace, with continuous monitoring of vacuum and temperature parameters and proper preheating of the diffusion pump. Enterprises must maintain bake-out operation logs, fully recording operating parameters and process details to ensure quality traceability. Aluminum brazing furnaces must be cooled to the process-approved temperature before being loaded for production.